Deployment
How to put a Microlander on the seabed from a small boat. The video is silent, portrait and 75 seconds long, so you can follow it on a phone on deck.
Signal is often poor at sea. Download the video (4.9 MB) to your phone before you set off.
The video works through one example, a site that is 10 m deep at high tide. The rope lengths follow from the depth, so work them out for your own site.
The rig, in the order it goes in
| Part | What it is |
|---|---|
| Lander | The frame with its SubCam fitted |
| Bridle | Two ropes tied to opposite sides of the frame, joined at a small 2 litre buoy |
| Rope | Floating rope, as long as the depth at high tide plus 20%. That is 12 m in the example |
| Clump chain | 25 kg, or 50 kg on an exposed site |
| S-shaped rope | Floating rope joined to sinking rope, each as long as the first rope. That is 12 m and 12 m in the example |
| Buoys | Two small surface buoys, 2 m apart |
Steps
- Tie a bridle to the frame. Two ropes, on opposite sides. Join them at a small 2 litre buoy.
- Add rope and a clump chain. Tie a floating rope to the bridle. Its length is the depth at high tide, plus 20%. Tie the clump chain to its other end. Use a 25 kg chain, or 50 kg on an exposed site.
- Then an S-shaped rope and two buoys. Join a floating rope to a sinking rope, each as long as the first rope. Tie the floating end to the chain. Tie two small buoys to the sinking end, 2 m apart.
- Lay it out in drop order. Lander first, buoys last. Flake the ropes so they run free.
- At the site, check the drift. Stop and see which way the boat drifts. You lay the rig along that line.
- Lower the lander slowly. Run the rope over a block for a little friction and ease it out by hand. A light lander can go over the side by hand.
- Feel it land, then give slack. Let the rope go slack the moment it lands.
- Drop the clump chain. Have it ready and drop it straight away. Close to the lander, never on top. In the example that is about 5 m away.
- Let out the S rope, then the buoys. Throw the buoys over, then mark the position.
A tight rope pulls the lander over. Give slack the moment you feel it land.
Once it is down, the floating rope arches up off the seabed between the lander and the chain. The S-shaped rope stops the buoys tugging the chain.
For choosing a site, camera settings and what to check before you go, see Field deployment. For frame sizes and parts, see Frame Configurations.